Radiological Assessment/Support and BAT/Optimisation

 Eden NE has been commissioned by EDF Energy Nuclear Generation Limited (EDF) to undertake marine dispersion modelling for several Advanced Gas-cooled nuclear Reactor (AGR) sites. This modelling considers how aqueous radioactive effluent could be discharged during decommissioning. It compares a range of alternative discharge arrangements and s...
Continue reading
Eden NE has provided support to the International Atomic Energy Agency (IAEA) through provision of an invited expert for an IAEA Cooperation Project with Fukushima Prefecture. Following the accident at TEPCO's Fukushima Daiichi nuclear power plant, the IAEA and the Fukushima Prefecture agreed to cooperate on radiation monitoring and remediation. Th...
Continue reading
Eden NE has led significant BAT/assessment/optimisation projects for Magnox Ltd, including the following. BAT Assessment of the Winfrith Sea Discharge Pipeline. Magnox Ltd are responsible for decommissioning the Winfrith nuclear site in Dorset. The decommissioning work involves determining optimised end states for site facilities. One of these faci...
Continue reading
ISOQAR Registered
Cyber Essentials Certified
SRP Affiliated Organisation
Cumbria Chamber of Commerce
Cumbria Growth Hub
EOA